Duplicate activities and events

Activities and events are managed in the "Workplan" section.

Note: To duplicate activities and/or events, you must have Manage access rights to the "Workplan" section or the respective parent activity (see "Roles, access levels, and access rights"). In addition, the current plan version must be in  Edit mode (see "Manage project plan versions").

Duplicating activities

1

Click Workplan in Home menu, this will open the "Workplan" section.

2

Click the quick action menu at the activity that you would like to duplicate and choose Duplicate.

3

The duplicated activity appears in the end of the "parent" activity list.

Tip: You can also duplicate an activity using its sidebar by clicking the action menu at the top right and choosing Duplicate.

Note: Read here how to create, edit, and move activities.

Duplicating events

1

Click Workplan in Home menu, this will open the "Workplan" section.

2

Click the quick action menu at the event that you would like to duplicate and choose Duplicate.

3

The duplicated event appears in the end of the "parent activity list".

Tip: You can also duplicate an event using its sidebar by clicking the action menu at the top right and choosing Duplicate.

Note: Read here how to  create, edit, and move events.