How completion % is calculated

Completion % (progress) in EMDESK reflects how far an activity (task, work package, sub-project), full project or the potfolio has progressed based on the latest reported status. It is automatically determined bottom-up from the lowest level (e.g. tasks) and updated at every parent level (work package). Completion values are always retrieved the most recent status update.

What is completion %?

Completion % shows how much of an activity is done at a certain point in time. It is entered manually as part of a status reports at the level of individual tasks or higher levels (work packages, or whole project). Once entered, EMDESK automatically calculates completion at higher levels.

How completion % is entered

Completion % is entered as part of a status report. You can report completion:

  • At the lowest levels (e.g. tasks)
  • On higher levels (work packages, project) — either manually or as a calculated result

Only the newest status report counts. Older status reports are ignored.

Calculation logic

  1. Direct completion for single item (no children)

If a task or activity has a reported completion of 50 %, it is simply shown as 50 %. There is no further calculation if it has no child items.

  1. Simple average for parent level (without planned effort)

When multiple child items have completion % and no planned effort assigned, the system calculates the parent’s completion through arithmetic average.

Example:

  • Task A: 25 %
  • Task B: 50 %

Work package completion = (25 + 50) / 2 = 37.5 %

  1. Effort-weighted calculation (if planned effort exists)

If planned effort is assigned (e.g. planned person-days), completion is weighted by effort to better reflect actual work volume.

Formula: Completion = Σ(child completion × child effort) / Σ(effort)

Example:

  • Task A: 25 % with 50 person-days
  • Task B: 50 % with 100 person-days

Work package completion = (25×50 + 50×100) / 150 = 41.7 %

Only items with effort receive weight. Items without effort are still included but are not weighted.

Example (mixed effort and no effort): • Task A: 50 % with 100 planned person‑days

  • Task B: 25 % with no planned effort
  • Task C: 75 % with 50 planned person‑days

Weighted tasks:

(50 % × 100) + (75 % × 50) = 5000 + 3750 = 8750

Total weighted effort = 150

Weighted result = 8750 / 150 = 58.3 %

Task B has no effort, so it is not weighted but its completion (25 %) still appears in the average context. It contributes proportionally but does not affect effort weighting.

  1. Calculation across multiple parent levels

The same logic applies recursively at every level, for example:

Sub-task → Task → Work Package → Project

Task → Work Package → Sub-Project  → Project

Completion always rolls up automatically using either weighted or simple averages, depending on effort availability.

Status update logic

  • Always the latest status update date 
  • When viewing historical periods, the latest report from that specific period is shown.
  • Older or overwritten reports have no effect.

Manual override

You can manually set completion % at any parent level: 

  • It replaces the system-calculated value at that level.
  • It automatically propagates upwards to higher levels. 
  • It remains until a more recent status report for that level or children is reported.
  • It does not affect individual child items.

Best practice tips

  • Enter completion at lowest levels for most accurate roll-up
  • Schedule planned effort on activities when possible to improve realism 
  • Use manual override only if strategic or exceptional
  • Update status regularly so reporting reflects actual progress 
  • Keep reporting dates consistent for reliable comparisons

Summary

Situation How it is calculated
Single task or activity Displays the completion % entered directly in the latest status report
Multiple children, no planned effort Average of all child completion % values
Children with planned effort Effort‑weighted average based on planned person‑days
Mixed effort and no effort Children with effort are weighted, others count as normal
Manual override Replaces calculated value at that level and propagates upward
Reporting view Always shows the latest status report within the reporting period
Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.